Wednesday, May 23, 2012

Entry 9: Meeting with group members

23 May 2012

Today, the entire group sat down to meet up once again. This meeting was for us to discuss on the progress on finding for the external help as well as for us to set down our work plans for the month of June, which is extremely crucial to the project.

Regarding the progress on finding and getting an external help, Keven and Gordon has been unable to get any help as they do not have any contacts in this area. While Ching Kai Xiang is currently speaking to Frankie, to see whether he is interested in helping us out.

As for the workplan during the June they are as follow:

Details
Due by
Action by
External help found
28/05/2012
All
Confirmation of Prototype
04/05/2012
All
Creation of website
10/06/2012
Keven Loo
Sourcing of materials
11/06/2012
All
Creation of prototype
15/06/2012
All


While here are the confirmed dates for meeting with our Mentor:

Date
Time
Action by
29 May 2012
1400 - 1500 / 1500 - 1600
Ching, Keven
5 June 2012
1400 -  1500 / 1500 - 1600
Ching, Keven
7 June 2012
1400 – 1500 / 1500 - 1600
All
12 June 2012
1400 – 1500 / 1500 - 1600
All

The reason as to why we aim to complete the core of our project during the June Holidays was because it would be when most of us are free and are thus able to commit ourselves to the project as compared to when school reopens where we will have other commitments such as our academics and CCAs.